HASSDAC was first time installed in Southern Railways from Mayiladuthurai to Thiruvarur Station by Mazenet in the year 2013,
which includes 3 blocks sections. It involved intense coordination between the OEM and Railways. The existing railway power cable design had an issue that was successfully resolved and completed on time.
Mazenet’s challenge was to work on one of the busiest traffic-ridden stations in the city. This involved the selection of lean traffic time
and the best team was deployed in order to get the project done without disturbing the train schedules and safety.
The contract was a first of its kind installation of MSDAC and provision of redundancy in track circuit in Southern Railways.
It is installed in Uthangal Mangalam Station for Southern Railways. The challenge faced was space constraint between the tracks to install the location box. Mazenet by its ingenuity successfully installed Mushroom Box for the station to resolve the issue which is not OEM's original BOM.
The commissioning of the 5 LC Gate interlocking. This work was a targeted work by the Trichy division. This has to fulfill the target set by Railway board
in the interlocking of gates in the division. Mazenet took the challenge planned it precisely to complete the commissioning within 90 days from the date of LOA.
The project site being a heavy traffic zone, Mazenet is successfully executing the project without disturbing the existing cables and infrastructure in the area.
Mazenet has pioneered in implementing Attendance and Incentive Management System (AIMS) 1000+ employees using our software.
The attendance, incentive calculation, and the overall production schedule of the entire S&T workshop work on AIMS software which includes Quality management, Leave management, Overtime & Marketing management.
Mazenet has made a first of its sort arrangement in the usage of EI data repository, version control software, and GIS Apps.
The entire data of EI logs across the station is maintained centrally in the Headquarters and in the Divisional offices for the Southern Railways. The project involves data replication, mini data center operation, and complaint tracking facility with the GEO location provided through GIS software. A Mobile application for both S&T and GIS has been developed and installed for respective SSE for ease of usage. The Network operates as a separate VPN through Rail Net which is secured with a firewall installed across the Divisions and Headquarters.
Mazenet has upgraded the entire Southern Railways Division Routers which installed 1841 Routers to 1921 Routers and were carried out
in all the PRS /UTS stations. The project was implemented successfully with the targeted time of 30 days for the entire router. It involves high passenger ticket regions like Mambalam, Tambaram and also at Park station where the downtime is very limited. With the minimal downtime, we successfully executed the changes in the router and the new configuration was loaded to support the Passenger Reservation system and Unreserved Ticketing system.